The investor is the Secretariat for Investments, the contractor is the Podgorica-based company “Tošković DOO”, and the total costs amount to around two million EUR.
“First of all, I want to express my gratitude to the families who agreed to sell their property along this stretch. Although they sold it at the market price, they could have gone through some other processes. I thank Mr Ivo Petović, Mr Cuca, and the Tripković family. I thank the contractor, who reacted quickly today, and I thank them for recognising how important it is that we open this construction site for Town Day. It will be finished by spring. It is certain, and there is no need for me to say too much about it, that the two-way Ivo Brkanović Street will significantly reduce traffic congestion in Kotor, and this is something we are all hoping for next summer
The value of the investment, for the works themselves, is around 850,000 EUR, and over a million EUR was previously set aside for the property
“So that is almost two million euros. But this is a “bypass”, the only one we can build here, and it is a key matter for this town and for traffic in this town”, said Jokić, congratulating the citizens of Kotor on 21 November, Liberation Day and Kotor Municipality Day, Archangel's Day (Aranđelovdan) and Our Lady of Health.
Among others, the ceremonial start of the works was attended by the President of the Kotor Municipal Assembly Vojin Batuta, Kotor Municipality deputy mayors Dr Igor Kumburović and Stojan Milović, Marina Bjelja – chief administrator, and the secretary for property and legal affairs Ivan Mikijelj, as well as representatives of the contractor and of the inspection bodies.
Project details:
Investor: Secretariat for Investments
Škaljari bb; tel: 067163537; e-mail: investicije@kotor.me
Designer: SIMM Inženjering doo,
Ivana Milutinovića br. 19, 81000 Podgorica
Tel/fax: +382 20 244 202; e-mail: simm@t-com.me
Simeun Matović
Reviewer: Reving doo Podgorica
Bulevar Revolucije 50/7-34 81000 Podgorica
Tel/fax: +382 20 245 647; e-mail: reving@t-com.me
Dr Biljana Ivanović, graduate civil engineer
Contractor: Toškovići doo Podgorica
Svetlane Kane Radević br.1, 81000 Podgorica
Tel/fax: +382 67 537 584;
e-mail: office@toskovici.co.me
Professional supervision: Građevinski nadzor i laboratorijska ispitivanja Podgorica
Ulica Zetskih vladara bb; Tel: +382 20 634 070; e-mail: nadzorilab@t-com.me
Marina Davidović, Spec.Sci. in civil engineering
BUILDING PERMIT: UP/I 03-333/26-760 of 17. 11. 2026.
CONSTRUCTION OF A LOCAL FACILITY OF GENERAL INTEREST
IVO BRKANOVIĆ STREET – PHASE II
The total length of the road axis is 280.95 m
Location: parts of cadastral plots 1319, 240/2, 242, 430, 241/2, 241/1, 243/2, 243/1, 450/1, 449, 450/2, 1315/2 and 420/1 Cadastral Municipality Škaljari I
Start date of works: 26. 11. 2026.
Completion date of works: 14. 03. 2027.